Groin Installation at Untung Jawa Island is Targeted to Finish Next Week
access_time August 22 2020 06:07 PM remove_red_eye 875
Reported by Suparni | Translated by Maria Inggita
Reported by Suparni | Translated by Maria Inggita
Groin construction which is being installed on the north and east beach sides of Pengantin Bridge, Untung Jawa Island, South Thousand Islands, is targeted to finish in the early next week.
Our target is to complete until the next three days
Thousand Island Water Resources (SDA) Sub-agency Head, Abdul Rauf conveyed, this 114-meter groin construction has been carried out in a week to restore the coastline in order to prevent abrasion.
"We have been working on it for a week. Our target is to complete until the next three days," he mentioned, Saturday (8/22).
Satpol PP Continues to Monitor Health Protocols Policy at Harapan Island PierCurrently, he explained, his personnel are working on 2nd and 3rd groins along 73 meters as well as leveling the sand with width 12-13 meters and height 40 centimeters.
"We deploy 14 personnel and its process reaches 80 percent," he conveyed.